A Day in the Life of a Civil Engineer – Day 44 and 45

Day 44

Hopefully today will be the last day I have to combine more than one day in a post – finally getting somewhat caught up. Today, I went through more emails. And I finished up the final approval letter for that development I worked on last Friday – it is for an industry in the city that is expanding. We had several meetings then throughout the day:

South Street Bike Trail

The county has been planning on building a bike trail underpass at one of the busiest roads we have in the city. Right now it is a four-land road with a 45 mph speed limit with plans to someday expand it to six lane. The number of cars is probably around almost 30,000 a day. So crossing it can be a challenge on a bike or as a pedestrian. In order to help get people across, the county is proposing this underpass. They have received funding for a portion of it from the state. So now, they are ready to move forward and finalize the design then go to construction. They told us today they are looking at building it in fiscal year 2013. We discussed some of the coordination needed between the city and the county to get the project done. They will be acquiring an easement from us, and we will be entering into an agreement. But the terms of all that still need to be worked out.

Utility Proposal

A utility has proposed an installation in our community that is unlike any other submittal we have yet received. So we met today to discuss the information. From my perspective, I had received an application for a right of way permit, but upon reviewing the plans I realized the proposed location is not within the right of way. So the application is not valid for this case.

Campbell Street Parking Lot

We also met to continue discussions about our plans to build a parking lot in our downtown area. We were mainly updating other staff members of the status. The city is still working out the easements with the adjoining owners that will be necessary to finalize the design.

Concrete Construction

A couple of us also had to inspect a few areas throughout the city that are targeted for improvements. We are in the process of obtaining bids for a small amount of concrete repairs we want to finish up this Fall.

Day 45

Finally today! This morning I worked on a multitude of issues. I completed our mid-year goals and strategies report and sent it off to my supervisor. Then I made sure my forms were ready to conduct performance evaluations later this month. All of us also worked on writing up our monthly reports for all our projects.

We had a bid opening today for our culvert project. There were a few bidders and the project seemed to come in near the engineer’s estimate so we will now prepare the information to take it to the council for approval. Before I mention anything else about this publicly, I am waiting for an official determination of the successful bidder.

And our contractor for our alley project finally was able to place half of the concrete pavement. After last week’s rain, we have had to wait a few days for the base to dry out. But today, it was finally ready for the pour.

In the afternoon, we had a staff development review meeting to go over a small proposed development in the city. It’s so helpful to have all of us get together at once and just discuss the project after we’ve had some time to look it over. Many people brought up good discussion points. So now the review engineer will incorporate the comments into his response and send it out later this month.