A project manager wants to display and communicate the results of PERT and Critical Path analysis in a simple chart that can be readily understood by those who are not involved in the detail of the project. Which of the following charts should she use?
A) Milestone chart
B) Flow chart
C) Gantt chart
D) Control chart
——————————
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try The PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
The Correct Answer is C.