Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com – The answer is at the very bottom:

——————————

You developed alternative schedules based on best-case and worst-case scenarios on your project. You want to keep these alternative schedules stored in your project documents, in case of changes in project resources. Where would you store alternative schedules?

A.) Schedule Baseline

B.) Schedule Data

C.) Project documents

D.) Project scope statement

——————————

Hint: Alternative schedules are part of one particular output of the Develop Schedule process. Look at those outputs to see where alternative schedules are located.

——————————

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

ANSWER AND EXPLANATION:

The correct answer is B

Explanation: Schedule data is an output of the Develop Schedule process and may contain alternative schedules such as best-case or worst-case scenarios.

Reference: PMBOK4 – pg:159