Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com – The answer is at the very bottom:

——————————

Tim is the project manager working on an electronic manufacturing project. In his project he wants to establish a warranty for some of the precision parts he is buying. What risk response strategy is he using?

A.) Mitigate

B.) Avoid

C.) Accept

D.) Transfer

——————————

Hint: Tim is shifting the negative impact of the risk.

——————————

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

ANSWER AND EXPLANATION:

The correct answer is D.
Explanation: Risk transfer requires shifting some or all of the negative impact of a threat, along with the ownership of the response. Taking out insurance or a warranty transfers the risk from the owner to the other party.
Reference: PMBOK4 – pg:303

Original post

Leave a Comment

Leave a comment

Leave a Reply