Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com – The answer is at the very bottom:

——————————

You have just completed the Perform Qualitative Risk Analysis process for your project. You think at least 20% of the risks that you have analyzed may create 80% of the project problems. You believe that the activity you just completed has not given you enough detailed information regarding this 20% of the risks and you have selected them for further analysis. What should you do next?

A.) Perform Quantitative Risk Analysis for all of the project risks.
B.) Perform Quantitative Risk Analysis for the selected risks only.
C.) Perform Qualitative Risk Analysis again.
D.) Ask your sponsor to guide you.

——————————
Hint: You should proceed to the Perform Quantitative Risk Analysis process.
——————————

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

ANSWER AND EXPLANATION:
The correct answer is B
Explanation: Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall project objectives. Perform Quantitative Risk Analysis is performed on the selected risks that have been prioritized by the Perform Qualitative Risk Analysis process as potentially and substantially impacting the project’s competing demands.
PMBOK Guide 4th Edition, page 294