Activity / Duration / Predecessor
A / 2 / Start
B / 4 / A,E
C / 6 / A
D / 3 / B,C
E / 7 / Start
F / 2 / E
What is the duration of the critical path?
A.) 11
B.) 14
C.) 9
D.) 15
——————————
Hint: Use PDM to calculate.
——————————
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
ANSWER AND EXPLANATION:
The correct answer is B
Explanation: The critical path is EBD and the duration of the critical path of the data given is 14.
Reference: PMBOK Guide 4th Edition, page 138