Which of the following activities is not concerned with developing the project charter?
A) Documenting the business needs
B) Project justification
C) Collecting output of the planning processes
D) Current understanding of the customers need
——————————
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try it for 3 days. We are a PMI Registered Education Provider.
The Correct Answer is C.