,

Free PMP Exam Sample Question

The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com – The answer is at the very bottom:

——————————

The method of constructing a project schedule network diagram that represents activities and connects them to show the dependencies is known as:

A) Arrow diagramming method
B) Schedule network templates
C) Precedence diagramming method
D) Activity list

——————————

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try it for 3 days. We are a PMI Registered Education Provider.

The Correct Answer is C.

Original post

Leave a Comment

Leave a comment

Leave a Reply